Engineering Recommendation G99 governs the connection of Power Generating Plant to the UK public distribution network. It applies when a generator runs in parallel with the mains — for peak load reduction, export, or closed transition transfer. Generators used solely for standby (open transition, never parallel with mains) generally do not require G99 compliance. If parallel operation is intended, G99 applies — requiring a DNO application, compliant protection relays and a DNO witness test before going live. iPower manages the full G99 compliance process.